The Turow Power Plant (447.5MW (Net), 262bar(a)/597°C/609°C) in Poland is currently
under construction, with the start of commercial operation scheduled for April 2020. The plant is
targeting the world's highest level of efficiency for a lignite-fired power plant. Mitsubishi Hitachi
Power Systems, Ltd. (MHPS) provides high-efficiency lignite-fired plant by applying its own
lignite-fired tower boiler technology, lignite mill burner technology, ultra-supercritical (USC)
technology and boiler flue gas heat recovery system. This report introduces the high-efficiency
USC lignite firing technology applied to the Turow Power Plant.