Top of page. Skip to main contents. Skip to main menu. Skip to footer.

HOME > Products > Energy > Once-Through Boiler > Outline of once-through boiler technologies
Main contents start here.

Outline of once-through boiler technologies

Introduction

The Shinchi Unit No.2 Boiler for Soma Joint Electric Power Company, representing the world's first application of the vertical waterwall design to a 1,000 MW Supercritical Sliding-Pressure Operation Boiler, began its commercial operation in July, 1995, and has been operating successfully since that time.Table 1 shows the major specifications for this boiler, andFigure 1 presents a side view of its general arrangement.
This paper describes the design features and operating results of the Shinchi Unit No 2 Boiler, focusing on the unique vertical waterwall design.
Other features include advanced technologies utilized in order to burn a wide variety of coals while maintaining a superior performance on environmental protection. As noted inTable 2, which outlines the construction and trial operation schedule, a total of 13 coals (seeTable 3) were used during the trial operation.

High reliability of the vertical waterwall design

In a supercritical boiler with sliding pressure operation, measures must be taken to deal with the deterioration of the heat transfer coefficient of water and steam in the partial load region where the fluid in the tubes becomes a two-phase flow at subcritical pressure. The spiral tube wall design shown inFigure 2 (a), using inclined boiler tubes, has been conventionally employed in order to increase mass velocity in tubes to the level required for maintaining proper heat transfer-nucleate boiling. The accompanying reduction in the number of tubes increases flow velocity by 2 to 3 times, for example, but this spiral tube wall design has relatively complicated structure, higher system pressure loss, and the higher auxiliary power consumption.
In considering these issues, MHI's attention was drawn to the superior heat transfer characteristics of rifled tubes (that promote heat transfer by means of a spirally grooved internal surface). Steam film is dispersed by means of the grooves on the inside surface of the rifled tubes, this inhibits film boiling and allows nucleate boiling to be maintained to a high steam quality level, thereby holding down metal temperatures. Accordingly, as illustrated inFigure 2 (b), the metal temperature of rifled tubes is kept sufficiently low and design flow velocity can be reduced to between 1,500 and 2,000 kg/(m2os) without encountering difficulty.
Following confirmation through laboratory testing, a vertical waterwall with rifled tubes was combined with a circular firing for practical application.
In addition to improved safety, this furnace design offers the following advantages:
  • (1)Because mass velocity is lower, pressure drop is reduced and auxiliary power consumption is improved.
  • (2)Simple configuration makes furnace support system much easier. Fewer attachments and less on-site welding work serve to shorten the installation period, and to improve reliability and maintainability.
  • (3)In coal fired units, slag deposit falls off the furnace wall more easily and local accumulation of slag on furnace wall is reduced.
  • (4)Because the ratio of friction loss in the heated section of the furnace compared with total pressure loss in the evaporator is low, flow stability is increased.

The furnace design described here is already used for Kawagoe Unit No 1 and Unit No.2 (gas-fired 700 MW boilers) of Chubu Electric Power Co., Inc., for Matsuura Unit No 1 (coal-fired 700 MW boiler) of Kyushu Electric Power Co., Inc., and for Hekinan Unit No 1 (coal-fired 700 MW boiler) of Chubu Electric Power Co., Inc., accumulating a great mount of experiences. The experience gained with these installations resulted in verification in advance and design improvements that were subsequently incorporated into the design for the world first 1,000 MW of this type.
Various tests conducted during the trial operation period for this 1,000 MW boiler demonstrated that reliability was equal or better than spiral type. As shown inFigure 3, which gives fluid temperature distributions at the furnace outlet for 100% ECR in the supercritical region and for 50% ECR in the subcritical region, stable and consistent furnace outlet fluid temperature distributions were achieved.
MHI is now aiming for achieving even better performance at Tohoku Electric Power Co., Inc. Haramachi Unit No.1 and Chugoku Electric Power Co., Inc. Misumi Unit No.1 1,000 MW boilers, and MHI recommends the use of this design to the customers because of its number of advantages.

Achievement of Low NOx and Low Unburnt Carbon in Fly Ash Combustion

Figures 4(a) and4(b) illustrate the Low NOx Burner and the Total Low NOx Combustion System combining the in-furnace NOx reduction system, advanced MACT, and high-fineness MRS pulverizer, used in order to reduce NOx emissions and unburnt carbon in fly ash.
  • (1)Low NOx Burner
    In this boiler, the PM Burner, a Low NOx Burner having the features described below, is installed in eight corners at six levels, including one level of standby, for a total of 48 burner units. Low unburnt carbon is maintained during low NOx operations, and superior ignition stability is maintained at low-load by combination of fuel-rich and fuel-lean flames.
  • (2)New Advanced MACT (Mitsubishi Advanced Combustion Technology)
    Above the over fire air (OFA) port integrated with the main burner, sufficient space for NOx reduction is maintained and additional air (AA) ports are positioned, resulting in even further lowering of NOx emissions.
  • (3)High fineness MRS Pulverizer
    As shown inFigure 5, the boiler is equipped with six 130 ton/hour pulverizers (including one standby). Rotary separators (MRS units) located at the top of each pulverizer provide for high fineness and improved separation performance. In particular, the amount of coarse particles left on 100 mesh (149 microns) is significantly reduced. In addition, an anti-vibration design is adopted, in which the roller and grinding table do not come into direct contact.
The results of firing tests conducted to adjust the Total Low NOx Combustion System are displayed inFigure 6. Against targets of 180 ppm for NOx and unburnt carbon in fly ash of under 5%, all test coals were well under. This was achieved even for N coal, which tends to have high NOx and unburnt carbon in fly ash figures, with test results of 150 ppm for NOx and 3% for unburnt carbon.

Boiler Performance

Figure 7 provides boiler performance test results at the acceptance test. A low excess air combustion (10 to 15% at rated capacity) was achieved due to the effectiveness of the MRS pulverizer in reducing the number of coarse particles. Meanwhile, boiler efficiency reached 91.6% with SL coal from US, against planned efficiency of 89.2%

Conclusion

Environmental and energy concerns over recent years have led to demands for higher plant efficiency and strict pollution control for coal-firing power plants, in addition to the capabilities of burning a variety of coals and of middle load operation. This report has introduced the Soma Joint Electric Power Co., Inc. Shinchi Unit No.2 Boiler, which fulfills all of these requirements. Attention from around the world is being directed to vertical waterwall type supercritical sliding pressure operation boilers, and the excellent operating results of this 1,000 MW installation have led to high evaluations for this design. Interest in the vertical waterwall design is expected to continue to mount, and the authors would be happy if that this report were of use in the planning of future fossil fuel-fired electric generation facilities.
MHI will continue to apply its valuable experience to future projects, which have higher steam conditions considering CO2 issues, and, as always, will be working to refine its technology and to meet the future needs of electric power industries for fossil fuel-fired plants.
In closing, we would like to express our sincere thanks to the peoples of the Soma Joint Electric Power for their cooperation in the construction of the Shinchi Unit No.2 boiler, from the basic planning process through to trial operation.

Business contact: Network

Business Segment: Power Systems
Return to top.
Page Top