MHI
receives Carbon II Power Station boiler upgrade order from the Mexican Federal
Electricity Commission |
|
MHI has received an order from the Mexican Federal Electricity
Commission (Commission Federal de Electrocidad) to carry out an up-grade project
on the #1 Boiler system equipment at the Carbon II Power Station located in Coahuila
State in Northern Mexico.
The boiler was made by MHI and delivered in 1992 (Capacity: 1,210 tons of steam/hour).
However, over ten years have passed. The current project is aimed at replacement
a economizer deteriorated and install a new control equipment for coal feeder.
These improvements will enhance operating reliability and also raise maintenance
efficiency.
This is a turnkey order that includes design, manufacturing, installation and
test operation. The project is scheduled for completion and final delivery in
February 2005.
|